State Nuclear Regulation Inspectorate of Ukraine conducts inspection at SSE ChNPP

Print

From 17 to 20 March 2014 the State Nuclear Regulatory Inspectorate of Ukraine conducts inspection at SSE ChNPP prior to issue individual permits for LRTP commissioning ("active" testing of LRTP ) and ICSRM (Stage 2 of the "hot" tests).

Comprehensive non active tests (using RW simulators) of LRTP systems and equipment and 1st stage of ICSRM "hot" tests were carried out in October 2013. In November 2013 ChNPP sent the package of application documents for continuation of these facilities commissioning.

Obtaining of individual permits will allow performance of the subsequent stages of ICSRM and LRTP commissioning, during which Radioactive Waste packages will be obtained.