Project No

Project title

Contractor

Cost (under the Contract)

Time frame

2128

Spent Nuclear Fuel Storage Facility (ISF-2)

Holtec International, USA

387 587 000 EUR

Beginning: 1996-11-12
Completion: 2017-12-31

2128

Liquid Radioactive Waste Treatment Plant (LRTP)

 

37 079 270 EUR
2 491 540 USD

Beginning: 1999-09-16
Completion: 2017-12-29

2404

Upgrading of Long-length Waste cutting facilities at Chernobyl NPP, U4.01/06W

AMEC Nuclear International Ltd, UK

3 518 760 EUR

Beginning: 2009-08-03
Completion: 2015-04-02

3471

Creation of an installation for the materials release from the regulatory control at Chernobyl NPP, U4.01/11Е

VF a.s,
Czech Republic

2 552 979 EUR

Beginning: 2015-12-18
Completion: 2018-05-11

 

Assistance in Chernobyl NPP decommissioning and RAW management UKR 9035

IAEA

241 000 EUR

Beginning: 2016-01-01
Completion: 20
17-12-31

 

Cooling pond decommissioning

using own resources

-

Beginning: 2013
Completion: -

 

Equipment dismantling

-

-

Beginning: 2012
Completion: -

 

 