Works on dismantling of the ChNPP II Generation Ventilation Stack (VS-2) were completed. 7 blocks with total weight of 330 tons were dismantled according to the Work Execution Plan.
Works on fragmentation of the dismantled blocks are underway within the specially prepared areas. The dismantled fragments are transported to Power Unit No.3 Turbine Hall by special vehicles for temporary storage. 440 fragments have been already placed at the Turbine Hall.
Prior to the placement, the fragments are subject to dust fixation by special compound, and pass the acceptance control for compliance with the criteria of temporary placement at the reserved areas.