About 75% of dismantled constructions was fragmented. About 800 fragmented elements were transported to the Turbine Hall.
Works aimed on VS-2 opening closure and permanent sealing were completed.
The Contractor has provided a tentative schedule with the date of works completion on 3 months ahead of schedule. Completion of all work under the Contract is planned for March 2014.