As on February 4, 2014, seven dismantled blocks of VS-2 were completely fragmented on specific-equipped site. Consequently, 1,599 fragments became available, which were transferred to Unit 3 Turbine Hall for temporary storage.
For information. VS-2 dismantling works were carried out under extremely complicated radiation conditions since end of October till beginning of December 2013. Totally, 330 tons of supports and braces of the ventilation stack were dismantled.