Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Drilling of holes for installation of sealing anchors at elev. +75.583.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;
• Final painting of walls and ceilings.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Within the project the following activity was performed at the construction site:

- Reconfiguration of fire protection valves of the ventilation system;
- Fire retardant sealing of penetrations of process pipelines;
- Calibration of the load cells and adjustment of crane positioning CR-07 and CR-08 room 305;
- Replacement of bolts on crane coupling CR-01;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Repairs and preventive works of SMTP — oil change is completed, leaks are eliminated;
- Measurements of holes in concrete structures (Completed on 24 modules) CSM;
- Elimination of comments on rainwater wells — concreting of covers
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- The preliminary checks of the Sliding Holder will continue;
- Commissioning works on double cover system for 200 l drums - checked in manual and automatic mode;
- Elimination of remarks on the video surveillance system;
- Preliminary checks of Luke protective SWP-CG-02 in pom. IS 102C6;
- Preliminary tests of LRW valves;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 126 people were involved, as well as 1 units of transporting equipment.

 

Select another date

Within the project the following activity was performed at the construction site:

- The work electrical part of the crane SWP-CR-04 was resumed;
- Reconfiguration of fire protection valves of the ventilation system;
- Adjusting the gaps and scalding (welding) of the sleeves of the penetrations of process pipelines;
- Fire retardant sealing of penetrations of process pipelines;
- Modification (sealing) of IAEA passages;
- Calibration of the crane load cells CR-08 room 305;
- Completed work on timber load monitoring LD-04 room 119;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Completed drilling holes and tapping in the door of CSM;
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- Inspection of the representative of the manufacturer of parallel manipulators, removal of comments on the results of inspection;
- Preparation of simulator for SFA capture;
- Completed elimination of remarks and re-testing of the TD-05/06 trolley in room 119;
- Completed elimination of remarks and re-testing of the double cover system TP;
- Elimination of remarks on the Cutting Machine;
- The preliminary checks of the Sliding Holder will continue — the calibration of the load cell;
- Commissioning works on double cover system for 200 l drums — checked in manual and manual mode;
- Elimination of remarks on the video surveillance system;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS
- Completion of comments on the SFP-CR-304 crane, testing of the Gostrud.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 143 people were involved, as well as 1 units of transporting equipment.

 

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Drilling of holes for installation of sealing anchors at elev. +75.583.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;
• Final painting of walls and ceilings.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Drilling of holes for installation of sealing anchors at elev. +75.583.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;
• Final painting of walls and ceilings.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Drilling of holes for installation of sealing anchors at elev. +75.583.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;
• Final painting of walls and ceilings.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Installation of the membrane on the roof of Block V.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Within the project the following activity was performed at the construction site:

- works on insulation of pipelines and forced gas drying system heaters;
- sealing of IAEA equipment, installation of locks;
- cable laying, installation of sockets;
- drilling of holes and screw cutting in the concrete storage modules doors;
- electrical works at the SWP-CR-04 crane;
- installation of electronic key system;
- reconfiguration of the Ventilation System fire protection valves;
- adjustment of gaps and welding of the sleeves of technological pipelines penetrations;
- fire retardant sealing of technological pipelines penetrations of process pipelines;
- scheduled works for the construction site improvement;
- compilation of the executive and hand-over documentation;
- development of technological units and systems testing programs;
- development of Customer's personnel training programs;
- pre-commissioning activity at the basic technological equipment and auxiliary systems;
- individual testing of the System for technological process monitoring and controlling at the - systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- software finalization and adjustment of the temperature control system for concrete storage modules;
- loading of double-wall shielded canister in the System of canisters manipulation and transportation and trial delivery into the concrete storage module;
- elimination of comments based on the results of individual tests of the device for spent fuel assemblies cutting SFP-CS-205;
- individual testing Systems for the canister CHT-TD-02 handling and transporting;
- elimination of comments based on the results of the trolley TD-05/06 individual testing;
- individual testing of the system of the fuel canister double lid;
- individual tests of protective lids SHIELDING PLUGS 305 SFP-XP-210/211;
- pilot operation of the Physical Protection System.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 141 people were involved, as well as 1 units of transporting equipment.