Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to test the main cranes is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway;
* Installation of cable ducts along the external Arch stairs construction.

- Technological building and auxiliary facilities:

* Technological building (TB) — work on arrangement of the eastern part of the building façade is close to completion. Installation of the cable ducts, cable laying. Preparation for 20 ton crane testing. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of door;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, dismantling of the transformers;
* Access Gateway for Fire brigades — installation of internal pipelines networks, arrangement of the external facade;
* Fire Extinguishing Pump Station — works on the electrical cables laying and installation of lighting and alarm system equipment;
* Sewage treatment facilities and pump station of storm water drainage — work on water level lowering  and foundation arrangement. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of fire and household water supply pipelines;
* Arrangement of the site of southern gallery hinged bearing in the Turbine Hall: delivery, assembly and installation of fire extinguishing towers is close to completion; works are carried out to install the design site fencing from the pioneer wall side; water removing tray dismantling;
* Construction of roads in Local zone — 78%.

Select another date

Within the NSC Project at the construction site the following works are being performed:

· Arch

Installation of the following main systems:

-  Power supply system;
-  Ventilation, gas purification and conditioning;
-  Fire safety system;
-  Water supply and sewerage system;
-  Communication and industrial TV system;
-  Physical protection and access control system;
-  Integrated control and monitoring system;
-  System of internal and transport connection;
-  Radiation monitoring system;

The systems of main cranes and small LLM are tested (16 small LLM have been tested so far).
Works on the internal and external lining have been completed.

MUFOP locking anchors are installed on the soffit structures of the West end wall.

The Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the process building).

Activities on the installation of the sealing membrane are underway.

Installation of cable boxes along the structures of the Arch external ladder.

 · Process building and auxiliary facilities:

- Process building (PB) - activities are carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying.

Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Activities on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal network pipelines, systems, metal structures. Installation of doors.

- Electrical Equipment Building - installation of fire alarm system, dismantling of transformers.
- Access Gateway for Fire Brigades - installation of internal networks pipelines, arrangement of external façade.
- Fire Extinguishing Pump Station – electric cable laying and installation of lighting system equipment.
- Sewage treatment facilities and pump station of storm water drainage - work on water level lowering and arrangement of the foundation. Installation of treatment facilities tanks.

Activities on arranging the NSC internal and external space are underway:

- Installation of pipelines for fire and industrial and potable water supply;
- Arrangement of the area of the southern gallery of hinged bearing in the turbine hall; delivery, assembling and installation of fire towers, installing the design fencing of the site from outside of the development wall, dismantling of the drainage gutter;
- Construction of roads and sidewalks in the local zone - 76%.

Select another date

Spent Fuel Processing Facility (SFPF):

- Project works performance development (technological layouts) for fire protection closure of penetrations.
- Unloading of the equipment and materials, equipment transfer into the installation area.
- Works on the bridge crane SFP-CR-11 modification in prem. 501 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of software and preparation for testing.
- Bridge crane SWP-CR-206 in prem. 403 adjustment and preparation for testing.
- Installation of concrete insert for arm hoist.
- Installation of main process equipment:
   * Electrical and installation work to install automation boards and FFS equipment sensors.
- Installation of BNG equipment power cables has been completed.
- BNG lighting cable laying and termination has been completed.

The following activities were also performed at the facility:

- Finishing of the SFPF building.
- Work on arrangement of the loading roof covering of the SFPF building with a pebble.
- Installation of steel structures  of the structural addition for balloons — arrangement of pavement, electrical works.
- Installation of sliding plates in CSM modules.
- Сompilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Work on commissioning and adjustment of the main process equipment and auxiliary systems.
- Individual tests of protective sliding doors SFP-SD-03 and SFP-SD-04 have been completed.
- Individual testing of 200-liter drums transportation system SWP-CR-222 (prem. IS102C7 / IS102C2) has been completed.
- Individual tests of the security windows SFP-SW-05 and SFP-SW-06 (premises 504/501) have been completed.
- Individual test of the indoor lighting system have been completed.
- Individual (independent) tests of FPS systems — central and back-up panels are underway.
- Individual tests of hot cells HCVS-S and HCVS-E ventilation system have been started.
- Individual tests of protective sliding doors SFP-SD-07 and SFP-SD-08 have been started.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 271 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work is carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying. Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire alarm system;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Sewage treatment facilities and pump station of storm water drainage — work on water drainage and arrangement of the foundation. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of pipelines for fire and industrial and drinking water supply;
* Arrangement of the site of the southern galleries of hinged bearing near the turbine hall;

* Construction of roads in Local zone — 68%.

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Connection of control panels to SOC;

* Works on the internal and external lining are close to completion;
* Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the technological building);
* Preparation and installation of sealing anchors on the roof of the technological building and access lock for the fire brigades;
* Work on the installation of the sealing membrane are underway;
* Installation of cable boxes along the constructions of the Arch external ladder.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work is carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying. Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Sewage treatment facilities and pump station of storm water drainage — work on water drainage and arrangement of the foundation. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of pipelines for fire and industrial and drinking water supply;
* Arrangement of the site of the southern galleries of hinged bearing near the turbine hall;

* Construction of roads in Local zone — 68%.

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Installation of MCS control panels in the central control panel. Connection of control panels to MCS. Works installation of small load-lifting mechanisms in the technological building are under way;

* Works on the internal and external lining are close to completion;
* Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the technological building);
* Preparation and installation of sealing anchors on the roof of the technological building and access lock for the fire brigades;
* Work on the installation of the sealing membrane are underway;
* Installation of cable boxes along the constructions of the Arch external ladder.

Select another date

Spent Fuel Processing Facility (SFPF):

- Development of work performance projects (technological sheets) for fire retention sealing of the penetrations.
- Unloading of the equipment and materials, equipment delivery into the installation area.
- Modification of the bridge crane SFP-CR-11 in the prem. 501 — installation of the electrical part is underway.
- Modification of the bridge crane SFP-CR-07 in the prem. 305 — installation of the electrical part completed.
- Modification of the gantry crane SFP-CR-08 in the prem. 305 — installation of the electrical part is underway.
- Electrical installation work on crane SWP-CR-206 in the prem. 403 and cables disconnection.
- Installation of electrical part — bridge crane MIS-CR-221 (prem 603).
- Installation of embedded parts for manual lifting tackles in SFPF building.
- Installation of main process equipment:
   * Installation of refrigeration supply system in the caisson 107c (connetion to CAV-RS-13, CAV-RS-14, CAV-RS-01).
   * Installation of pipelines of the technological blowdowns system in SFPF.
   * Installation and wiring work on SFPF equipment pinout.
   * Installation of a stationary high-pressure apparatus Kärcher is completed.
   * Modification of the mounting seat for the protective lid of the canister manipulation and transportation (CMTS) system — manufacturing of the components for modification, dismantling of the existing metal structures.
   * Installation of power and control cables of BNG equipment.
- Laying and pinout of BNG lighting cables in the SFPF premises.
- Works on the installation openings closing in prem. 603 — roof arrangement.

The following activities were also performed at the facility:

- Finishing of the SFPF building premises.
- Installation of fore-roof metal structures for pressure vessels.
- Compilation of executive and hand-over documentation.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Theoretical training for the personnel.
- Pre-commissioning work on the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Completion of individual tests of the lock for small-sized elements (LSE) SWP-TD-221.
- Individual testing of the hot cell filters CAV-FR-213 and lids of wells No. 1 & 3 (SFP-CG-212, SFP-CG-213).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 268 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- The electrical installation work at the crane MIS-CR-240 in prem. IS102c9 are completed.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-07 modification in prem. 305 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of the electrical part.
- Finishing (including the floor painting) in prem. 119 of the SFPF building is completed.
- Installation of main process equipment:
     * Installation of bottom frame of the caisson 107c.
     * Installation of FFS pipelines in prem. 505 A and 505 B of the SFPF building without the valve mounting has been completed (delivery is expected).
     * Re-tracing the fire-fighting pipeline inside the SFPF building.
     * Installation of power and control cables of BNG equipment.
- Works on the installation openings closing in prem. 603 — рarapet arrangement.

The following activities were also performed at the facility:

- Installation of the external fire escape stair P2 and the installation of the SG-5 ladders has been completed .
- Finishing of the SFPF building premises.
- Arrangement of the arms room in the checkpoint.
- Installation of fore-roof metal structures for pressure vessels.
- Extension of seismic restrains on CSM modules.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Conducting of theoretical training for the Customer's personnel.
- Pre-commissioning work at the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Conducting of individual tests of the lock for small-sized elements (LSE).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 266 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work associated with arrangement of the facade of the building eastern part. Installation of cable ducts, cabling is underway. Crane beams for the 20 ton crane are being installed. Reassembly of 20 ton crane. The crane has been lifted to the design reference mark. Installation of Fire Alarm System. Installation of air ducts of the ventilation system. Works inside the building on polishing, priming, filling up with putty, pouring, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Storm Water Dispersal Plant — activities on water drawdown and foundation construction, dewatering of the site sump. The tanks of dispersal plant are being installed.

- Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of Arch end walls;
* Arrangement of the area for southern gallery of articulated supports near the turbine hall;

* Construction of roads in Local zone — 65%.

- Erection of Arch steelwork:

* Installation of the following main systems:
• Power supply system;
Ventilation, gas purification and conditioning;
Fire safety system;
Water supply and sewerage system;
Communication and industrial TV system;
Physical protection and access control system;
Integrated management and control system;
System of internal and transport connection;
Radiation monitoring system;
* The Contractor also completed installation of the MCS trolleys moving system in the northern garage. The MCS control cabinets are being installed in the central control room. Connection of control boards to the central control room;

* Work is underway to install small lifting devices in the technological building;
* Completion of external and internal facing;
* Preparation for installation and installation of sealing anchors on the roof of TB and Access Gateway for Fire Brigades;
* Installation of the sealing membrane is underway.

May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017