February 21, 2013

Select the another date

Within the framework of the NSC project at the construction site the following activities were implemented:
-        preparation of lifting towers for assembling;
-        assembling of infill elements of main structures;
-        clearance of site and crane rails from snow and ice;
-        Installation of arch metal constructions up to 2-st lifting - according to the design - 4097 tons, installed 103,98 tons (2,54%)

Nearest Events

December 14 - Day of honoring the participants of Chornobyl accident consequences elimination
December 14, 1977 – signing of ChNPP 1st Power Unit Commissioning Certificate

News distribution