February 28, 2013

 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- preparation for assembly of lifting towers
- assembly of the lifting towers
- dismantling of the lifting towers’ sections
- removal of snow and ice from the site and crane runways
- installation of outer cladding purlines
- assembly of Floline 70 steel decking laminates

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons, 123,98 tons (3%) performed

Assembly of the Arch section outer cladding after 1st lifting
According to the design – 7,847.07m2 area
60.47% performed

Nearest Events

April 26, 1986 (1.23.40 a.m., Moscow time) – accident at Chornobyl NPP Unit No.4 in the course of design testing of one of the safety-related systems
In the beginning of May, 1977 the assemblers, builders, servicemen and operational personnel of ChNPP begun precommissioning works at Unit 1

News distribution