Within the NSC Project at the construction site the following works are being performed:
- bolt tightening of West end wall structures;
- Lifting and installation of TP-4 tilting panel of Eastern end wall;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14316,80 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13712,32 tons

May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015
  

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of West End wall panel;
- Installation of temporary equipment for TP-4 tilting panel lifting;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,994.72 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,453.06 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of West End wall panel;
- Installation of temporary equipment for TP-4 tilting panel lifting;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,858.4 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,453.06 tons

April 23, 2015
April 23, 2015
April 23, 2015
April 23, 2015
  

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of West End wall panel;
- Installation of supporting tower 11 for Western end wall;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,850.39 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,453.06 tons

April 16, 2015
April 16, 2015
April 16, 2015
April 16, 2015
April 16, 2015
April 16, 2015
  

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of West End wall panel;
- Completing and assembly of casing girders;
- Preliminary erection and assembly of steel plating packages for casing, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,803.0 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,445.53 tons

April 09, 2015
April 09, 2015
April 09, 2015
April 09, 2015
April 09, 2015
April 09, 2015