1. Installation of foundations in assembling area
- according to the design - 10 762,6 m3, installed - 10 414 m3 of concrete (96,5%)
- according to the design - 2 874,9 tons, manufactured - 2 825 tons of reinforcing roads (98,3%)
2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed - 2 763 m3 of concrete (36%)
- according to the design - 1593, 128 tons, manufactured - 934 tons of reinforcing roads (58,6%)
3. Installation of arch metal constructions (up to 1-st lifting)
- according to the design - 5 500 tons, installed - 3 692,5 tons (67,1%)