September 27, 2012

Select the another date

1. Installation of foundations in assembling area
- according to the design - 10 762,6 m3, installed - 10 558 m3 of concrete (98,1%)
- according to the design - 2 874,9 tons, manufactured - 2 825 tons of reinforcing roads (98,3%)

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed - 3 189 m3 of concrete (41,5%)
- according to the design - 1 593,128 tons, manufactured - 1 048,252 tons of reinforcing roads (65,8%)

3. Installation of arch metal constructions (up to 1-st lifting)
- according to the design - 5 500 tons, installed - 3 918,83 tons (71,3%)