October 04, 2012

Select the another date

1. Installation of foundations in assembling area
- according to the design - 10 762,6 m3, installed 10 558 м3 of concrete (98,1%)
- according to the design - 2 874,9 tons, manufactured 2 825 tons of reinforcing roads (98,3%)

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 4 091 m3 of concrete (53,28%)
- according to the design - 1 593,128 tons, manufactured 1207,28 tons of reinforcing roads (75,8%)

3. Installation of arch metal constructions (up to 1-st lifting)
- according to the design - 5 500 tons, installed 4241, 34 tons (80%)