1. Installation of foundations in assembling area
- according to the design - 10 762,6 m3, installed 10 558 м3 of concrete (98,1%)
- according to the design - 2 874,9 tons, manufactured 2 825 tons of reinforcing roads (98,3%)
2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 5 641 m3 of concrete (73,5%)
- according to the design - 1 593,128 tons, manufactured 1351.586 tons of reinforcing roads (84,8%)
3. Installation of arch metal constructions (up to 1-st lifting)
- according to the design - 5 500 tons, installed 5019,46 tons (94,7%)