December 06, 2012

Select the another date

1. Installation of foundations in assembling area - completed

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 6 318,5 m3 of concrete (82,3%)
- according to the design - 1 593,128 tons, manufactured 1 492,221 tons of reinforcing roads (93,7%)

3. Installation of arch metal constructions (up to 1-st lifting) - completed; first lifting performed