Yanuary 17, 2013

Select the another date

 

Within the framework of the NSC project at the construction site the following activities were implemented:
-        preparation for dismantling of lifting towers;
-        dismantling of the lifting towers;
-        cleaning of the site and crane rails from snow and ice;
-        preparation for dismantling of temporary metal structures of the Arch;
-        dismantling of safety fencing panels of the Arch’s roof;
-        installation of temporary crossover for construction machinery at the South trench of the Local Zone (earth excavation).