Within the framework of the NSC project at the construction site the following activities were implemented:
- preparation of lifting towers for assembling;
- assembling of lifting towers;
- assembling of infill elements of main structures;
- clearance of site and crane rails from snow and ice;
- assembling of external cladding purlines;
- device of temporary crossover for construction machinery in the east of
excavation pit along axis 34;
- Installation of arch metal constructions up to 2-st lifting - according to the design - 4097 tons, installed 93,98 tons (2,29%)