Within the NSC Project at the construction site the following works are being performed:
Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
3,793.15 tons (92.58%) performed
Mounting of the roof covering of the Arch:
Surface area of roof cladding before 2nd lifting - 13,952.2 m2, 92% performed.
Surface area of internal cladding before 2nd lifting – 12468.15 m2, 81.1% performed
Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 92 piles (44.23%)