10 May 2016, Works Started on Discharge of Damaged Spent Nuclear Fuel from ChNPP Unit 1

On the 10th of May 2016 works started on discharge of damaged spent nuclear fuel from Unit 1, and its transportation to the ISF-1 cooling pool.

The activities are being performed according to the individual permit series OD No. 000040/9 For Works and Operations on Discharge of Damaged Spent Nuclear Fuel from Power Units 1 and 2, and Its Transportation to the Wet Type Interim Spent Fuel Storage Facility (ISF-1) to be Safely Placed and Stored, issued by the State Nuclear Regulatory Inspectorate of Ukraine to SSE ChNPP on the 14th of April 2016.

SNRI of Ukraine Press Service