NSC construction Project: equipment testing is underway

In parallel with installation work performance individual tests of equipment and systems for New Safe Confinement are underway. As of August 1, 2017, the following equipment and systems were tested within the project:
- NSC Main Crane System, including two bridges, two crane trucks, mobile instrumentation platform, northern and southern maintenance garages with 25 tons crane;
- passenger lift in the western end wall of the Arch;
- 20-ton bridge crane in the Technological building;
- 12 types of electric and manual lifting devices;
- NSC power supply system 6 kV.

 NSC commissioning is scheduled for December this year.

Випробування систем НБК
Випробування систем НБК
Випробування систем НБК