Works on conditioned Spent Nuclear Fuel (SNF) unloading from ChNPP Unit 1 are underway. As of 20.03.2013 it has been transported 414 of 1325 Spent Fuel Assemblies in ISF-1. Works are carried out in accordance with "Measures, ensuring process of Nuclear Fuel removal from Chernobyl NPP Units 1,2", put in force the Decree No 51 dated 26.01.2012, in compliance with terms of the Separate Permission 000040/1 -21of the State Nuclear Safety Inspection at Chernobyl NPP.
According to the schedule it is planned to complete this work 30.11.2013.