On November 3, a progress meeting of ChNPP Generation II structures reinforcement and sealing project was held. The representatives of the power plant management, of the European Bank for Reconstruction and Development, of contracting organisations involved in this project, of SIP project management unit, of NOVARKA as well as of “KIEV ENERGOPROJECT” institute, who is the project designer, attended this meeting. The meeting was chaired by Igor Gramotkin, ChNPP Director General.
The meeting was devoted to discussion of the possibility to speed up the implementation progress of the ChNPP Generation II structures reinforcement and sealing project as this project has critical interrelationship with NSC construction. It is impossible to slide the Arch to the design position and to commission it until the side walls are erected.