After State Architectural and Construction Inspectorate had issued permit to perform activities for “Reconstruction of ChNPP Unit 4 Turbine Hall enclosing contour between axes 46-52 and А-B” the physical works were commenced.
The personnel have been mobilized to the site where activities will be carried out; the road surfacing is being improved within the local area of Shelter Object; the access ramps and runways as well as a ground for framework assembling are being arranged. The plant-manufacturer fabricates steelwork components of the turbine hall roofing spatial module.
Ukrderzhbudekspertyza issued positive experts’ conclusion for Detailed Design of “Reconstruction of ChNPP Unit 4 Turbine Hall enclosing contour between axes 46-52 and А-B” developed by Kyiv Institute “Energoproekt” and this detailed design was approved by SSE ChNPP order in September 2013.
In November 2013, based on the tender results a contract for civil works was concluded with Ukrtransbud Corporation.
The activities associated with reconstruction of enclosing contour of ChNPP Unit 4 Turbine Hall are scheduled to be completed by the end of current year.
For information. On February 12, 2013, Unit 4 Turbine Hall wall structures and some part of light roof collapsed partially. The area of damage made about 600 m2. From February 12 till 20, two commissions worked to investigate the causes of incident, they analyzed the situation due to which the building structures collapsed and issued their propositions for eliminating consequences.