Completed Projects

Project No

Project title

Cost 
(under the Contract)

Time frame

 

Completion of the Industrial Heating Plant construction
WBS 03.02.02

30 000 000 USD

Beginning: -
Completion: 2000-04-21

3224

Chernobyl decommissioning Visualization Center creation and development,
NMFA 711

100 000 EUR

Beginning: 2014-01-01
Completion: 2015-12-31

2287

Industrial Complex for Solid Radioactive Waste Management, Lots 1, 2

38 294 000 EUR

Beginning: 2001-03-05
Completion: 2009-02-25

2153

Technical assistance on the site to Ukrainian organizations in Chernobyl NPP RAW Management facilities creation, monitoring within the Exclusion Zone and NPP equipment repair, 
U4.01/02

5 245 750 EUR

Beginning: 2004-12-01
Completion: 2009-12-31

2188

Complex for metal drums and reinforced concrete containers production for ChNPP Radioactive Waste storage U4.01/04W

5 568 050 EUR

Beginning: 2007-12-28
Completion: 2012-05-23

2306

Additional work in the framework ICSRM project in Chernobyl. Delivery of the ventilation system for buildings 84, U.4.02/07A

400 000 EUR

Beginning: 2009-01-19
Completion: 2010-06-19

3252

Support in the Radioactive Waste characterization and release from regulatory control in Ukraine, U4.01/10B + E

1 469 900 EUR

Beginning: 2014-04-18
Completion: 2017-01-18

2379

Decommissioning Information Support System of Chernobyl NPP, U4.04/06

1 532 530 EUR

Beginning: 2009-05-26
Completion: 2012-02-25

2437

Additional work in the framework ICSRM project in Chernobyl - support providing in licensing activities, as well as "hot" tests controlling, U4.02/07

1 390 000 EUR

Beginning: 2010-01-18
Completion: 2014-11-17

2711

Improvement of the overall strategy for Radioactive Waste Management at operating and shutdown NPPs in Ukraine, U4.01/08-D

1 775 180 EUR

Beginning: 2012-06-30
Completion: 2015-08-20

-

Reconstruction of Transport and Process Equipments of the Interim Storage Facility for Spent Fuel (ISF-1)

-

Beginning: 2010
Completion: 2012

3318

Creation of an industrial facility for ChNPP Water and liquid Radioactive Waste purification from transuranium elements and organic compounds - Stage I, 
U4.01/11С

1 769 493 EUR

Beginning: 2014-09-01
Completion: 20
17-09-01

3213

Support in Radioactive Waste Management in Ukraine, U4.01/10 СDF

3 865 200 EUR

Beginning: 2014-04-16
Completion: 20
17-04-16