In the framework of implementing the project relating to construction of the Liquid Radwaste Treatment Plant (LRTP) at Chernobyl NPP, on August 7, 2017, according to the results of open tendering, a contract was concluded with CC “Ukrbudmontazh” to perform activities associated with its completion and bringing the fire systems in compliance with effective regulatory structure.
Construction of LRTP was carried out at the expense of international technical assistance from Nuclear Safety Account funds and was suspended due to depletion of the allocated budget. Resumption and completion of LRTP from national budget of Ukraine became available after the approval of the updated project.
Work performance under the contract with CC “Ukrbudmontazh” will enable to commission the facility and commence treatment of liquid RAW on SSE ChNPP site. Completion of works under the contract is scheduled for May 2018.
For more details about Liquid Radwaste Treatment Plant, please click here.




In parallel with installation work performance individual tests of equipment and systems for New Safe Confinement are underway. As of August 1, 2017, the following equipment and systems were tested within the project:
On July 19, the testing of TK-8 docking mechanism started. This unit is one of the most important pieces for handling of Chornobyl NPP spent nuclear fuel.