This is to inform you that that a press-tour to the Chernobyl NPP for members of the Ukrainian and foreign media will be organized on December 22, 2016.
During the press-tour the media members will visit:
- Chernobyl NPP industrial site (NSC);
- Interim Spent Fuel Dry-type Storage Facility construction site (ISF-2).
The meeting of the Board of the State Nuclear Regulatory Inspectorate of Ukraine was held on December 1, 2016, in course of which the issue "On the approaches to the licensing of Confinement operation, including Chernobyl NPP "Shelter" object" has been considered.
Currently activity at the Chernobyl NPP "Shelter" object is carried out under the License EO series No 000033 issued by the State Nuclear Regulatory Committee on December 30, 2001. Period of license validity is till the New Safe Confinement (hereinafter: NSC) commissioning.
According to the plans of the State Enterprises Chernobyl NPP and the Contractor for NSC designing and construction, the facility construction completion is expected in November 2017. After the NSC first stage commissioning Chernobyl NPP should obtain a new license for its operation.
The regular Assemblies of Chernobyl Shelter Fund and Nuclear Safety Account contributing countries took place at Chernobyl NPP on November 29.
The main topic of the CSF Assembly discussion was a progress in New Safe Confinement construction project, the Arch of which is set in the design position over ChNPP Unit 4 destroyed due to beyond-design-basis accident.
Mr. Hans Blix, the Chairman of the Assembly of the Chernobyl Shelter Fund Contributors, has mentioned that NSC Arch sliding is really historical event since the New Safe Confinement would enable to protect Ukraine and the world in future against nuclear hazard: “After 30 years since tragedy, the pain and scale of losses are still biggish. However, the recovery process is being continued. Junction of two halves of the big arch, installation of mammoth cover over historical reactor is like repair of a wound, a nuclear wound, concerning us all.”
IAEA expert mission "Reuse and changing the purpose of the emptied facilities for the decommissioning needs" was held in November 16 - 18 at ChNPP Training Center in Slavutich town.
The main purpose of the mission was sharing of experience and study of the best international practices in reuse of nuclear sites for other purposes. Chernobyl NPP’s specialists presented ChNPP approaches and plans for reuse of site area and repurposing of the existing buildings and structures for industrial development in the field of radioactively contaminated material, Radioactive Waste and Spent Nuclear Fuel Management.