The State Nuclear Regulatory Inspectorate of Ukraine issued a separate permission giving a right to implement activities in accordance with the Programme of FS&P Stage. It means that the Chernobyl NPP completes the shutdown activity and officially proceeds to the decommissioning stage.

The permission was issued pursuant to the State License for Decommissioning No.000040 dated March 22, 2010, obtained by the SSE ChNPP based on the approved Design of Final Shutdown and Preservation (FS&P) Stage. The State Regulatory Body’s recognition of significant progress in planning the ChNPP decommissioning process, successful work on the release of ChNPP Units from spent nuclear fuel and its placement into a special storage facility for safe storage – ISF-1 – is the key and necessary condition to obtain such permission.

On the 12th of November 2013 the fifth block (B-5) of the ChNPP II Generation Ventilation Stack (VS-2) weighting 48 tons was dismantled.

SIP PMU “New Ventilation Stack” Project Manager Vitaliy Shurygin noted that works on VS-2 are unique, because they are carried out under conditions of ionizing radiation and radioactive contamination, as well as in confined spaces in the area with a large number of overhead passes, buildings of different purpose and transportation lines. With the objective to reduce the dismantling time, it is performed in larger units by the crane with lifting capacity of 1,600 tons.

During October 1-3, 2013, a technical workshop “Results of Activity Related to ChNPP Cooling Pond Decommissioning Options” is taking place in Kiev. The workshop is arranged under performance of IAEA Technical Cooperation Project UKR/9/030 “Assisting ChNPP in Decommissioning and Safe Management of Radioactive Waste”.

The surveys and pre-design developments carried out during last years to determine a strategy of Cooling Pond (CP) decommissioning showed that implementation of this project will enable not only to reduce capital and operational costs related to control nominal water level in the cooling pond, but also reduce amount of radioactively contaminated waters being generated as a result of continuous water-logging of lower premises of ChNPP Units, mitigate the risks associated with potential failure of protecting dam and reduce carry-over of radioactive substances from CP in Pripyat river due to more filtration of the pond. 

On September 28, 2013, the ChNPP personnel completed the works on removing conditioned spent nuclear fuel from Chernobyl NPP Unit 1. 

The works were commenced on December 22, 2011. During this period, 1,333 spent fuel assemblies (SFA) were transferred from Unit 1 to Compartment 5 of Interim Storage Facility 1 cooling pool. 

The works on releasing Chernobyl NPP Unit 2 from conditioned spent nuclear fuel were completed in November 2012 and in September 2010 for Unit 3. Prior to work performance on SNF discharge, the plant personnel developed and implemented ISF-1 modernization design aimed at improving safety of this facility in accordance with the requirements of the State Nuclear Regulatory Inspectorate of Ukraine. 

Manufacturing of separate types of equipment required for SNF discharge by ChNPP personnel efforts ensured essential time and budget savings. Particularly, the plant departments produced 3,294 “short” canisters. 

Nowadays, the ChNPP personnel work together to address an issue on handling damaged nuclear fuel remained at Units 1 and 2.

On the 25th of August the Minister of Foreign Affairs of Japan Fumio Kishida made a technical visit to the Exclusion Zone area and the Chernobyl NPP site itself.

During a meeting at the ChNPP Model Hall the guests received from the ChNPP General Director Igor Gramotkin the general information on work status at the industrial site of the Plant, progress of international projects aimed at the Chernobyl NPP decommissioning and Shelter Object transformation into an ecologically safe system.