Pre-assembling of spatial unit to cover opening arisen as a result of Unit 4 Turbine hall wall constructions collapse is started.
Upon information provided by plant’s Construction service as of January 9, 2014 all necessary metal constructions were delivered to Chernobyl NPP’s industrial site, 10 percent of them are already installed in the future spatial unit. Total weight of the entire unit will be 53 tons. It should fully close an emergency opening arisen as a result of abnormal event, occurred February 12, 2013.
Work within theproject "RecoveryofthesafeenclosureofChNPPUnit 4 TurbineHallbetweenaxes 46-52 andA- B" is performedbythecontractor - "Ukrtransbud" CorporationincooperationwithChernobylNPP. Earlier, in accordance with the project schedule contracting organization personnel dismantled emergency concrete wall panels, joining constructions between the columns, as well as reinforcement of the upper damaged panels.