Within the NSC Project at the construction site the following works are being performed:
- Installation of bearers for cladding (Western part of the Arch);
- Installation of metal constructions of the northern section of the main cranes system;
- Pre-assembling of the cladding panels;
- Installation of external and internal cladding (western and eastern parts of the Arch);
- Delivery and assembling of galvanized air ducts, preparation for installation and installation of air ducts and supporting structures within the annular space of the Arch western part;
- Arrangement of service zone foundations (southern belt foundation grill reinforcement and concreting);
- Arrangement of the technological building and auxiliary facilities:
     * Technological building - installation of the foundation slab reinforcement (concreting of the second block foundation slab is scheduled on 27.06.2014 (950 m3 of concrete));
     * Fire fighting pump station building - soil grouting;
     * Access gateway for fire brigades - soil grouting.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 7,275.606 tons.

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 8,770.7 m3(74.36%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 2,246.278 tons (91.8%).

   

June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, preparation for installation and installation of ducts in the western part of the Arch annular space;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Arrangement of engineering building and auxiliary facilities.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,998.677 tons.

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,792.71 tons (93.08%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 8,589.7 m3(72.82%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 2,185.072 tons (89.29%).

  

June 19, 2014
June 19, 2014
June 19, 2014
June 19, 2014
June 19, 2014
June 19, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- sliding ways arrangement;
- Lifting towers Movement;
- I
nstallation of sub-crane beams for main cranes system;
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, preparation for installation and installation of ducts in the western part of the Arch annular space;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Arrangement of engineering building and auxiliary facilities;
- RAW loading and transportation at WDF Buryakovka.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,794.675 tons.

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,792.71 tons (93.08%).

Concreting of the Technological building foundation slab:
Design volume of concrete – 6,506 m3, placed – 634.2 m3 (9.8%); 
Design amount of rebars - 1,440.2 tons, rebar fabrication – 428.3 tons (29.7%).

 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- Lifting towers Movement;
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, ducts installation in the annular space of Western part of Arch;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Arrangement of engineering building and auxiliary facilities. Technological building ground grouting has been completed.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,667.624 tons.

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 7,483.7 m3(63.44%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,973.722 tons (80.66%).

June 05, 2014
June 05, 2014
June 05, 2014
June 05, 2014
June 05, 2014
June 05, 2014
  

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- Dismantling of Arch jacking system, lifting towers Movement;
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, ducts installation in the annular space of Western part of Arch;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Isntallation of CFA piles of service area foundation (Southern trench). Work was completed 05/24/2014;
- Arrangement of engineering building and auxiliary facilities. Technological building ground grouting has been completed.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,595.326 tons.

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 7,287.7 m3(61.78%);
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,957.392 tons (79.99%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 216 piles (100%)

May 29, 2014
May 29, 2014
May 29, 2014
May 29, 2014
May 29, 2014
May 29, 2014