Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic structures of the arch
- Assembling of hanger supports of crane beams
- Assembling of upper platforms of hoisting towers
- Assembling of a container of jacking system
- Assembling of binding rafters of the cladding
- Assembling of binding rafters of inner lining
- Works on assembling of Floline 70 steel flooring packs were performed
- Profiling of Kalzip panels
- Preparatory works for engineering building were performed

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
831,32 tons (20,3%) performed

Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2
м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 37,1%

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic structures of the arch
- Assembling of hanger supports of crane beams
- Assembling of upper platforms of hoisting towers
- Assembling of a container of jacking system
- Assembling of binding rafters of the cladding
- Assembling of binding rafters of inner lining
- Works on assembling of Floline 70 steel flooring packs were performed
- Profiling of Kalzip panels
- Preparatory works for engineering building were performed

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
645.3 tons (15.7%) performed

Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2
м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 36.2%

Select the another date

 

Within the NSC Project at the construction site the following works are being performed:
- installation of outer cladding purlines; 
- installation of inner cladding purlines;
- erection of lifting towers’ sections;
- assembly of Floline 70 steel decking laminates;
- preparatory works before arrangement of a fire pump house;
- lifting of a jacking system container for a tower.

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
393.98 tons (9.6%) performed

Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 35.6%

 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- preparation for assembly of lifting towers
- assembly of the lifting towers
- dismantling of the lifting towers’ sections
- removal of snow and ice from the site and crane runways
- installation of outer cladding purlines
- assembly of Floline 70 steel decking laminates

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons, 123,98 tons (3%) performed

Assembly of the Arch section outer cladding after 1st lifting
According to the design – 7,847.07m2 area
60.47% performed

Select the another date

Within the framework of the NSC project at the construction site the following activities were implemented:
-        preparation of lifting towers for assembling;
-        assembling of infill elements of main structures;
-        clearance of site and crane rails from snow and ice;
-        Installation of arch metal constructions up to 2-st lifting - according to the design - 4097 tons, installed 103,98 tons (2,54%)