Foundations of installation area
- Installation of temporary shielding.
-
Reinforcement.
-
Installation of shuttering.
-
Concreting. Concrete B50 (106m3).

2. Arrangement of foundations in transport area
-
Works weren’t performed

3. Arch
-
Geodesic checking of metal constructions.
-
Dismantling of anchor block, installation of jack steel wire ropes.
-
Preparation for jacking beams dismantling.
-
Dismantling of lifting towers containers
-
Physical works on shuttering installation weren’t performed.

 

Select the another date

1. Installation of foundations in assembling area - completed

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 6 318,5 m3 of concrete (82,3%)
- according to the design - 1 593,128 tons, manufactured 1 492,221 tons of reinforcing roads (93,7%)

3. Installation of arch metal constructions (up to 1-st lifting) - completed; first lifting performed

Select the another date

1. Installation of foundations in assembling area
- according to the design - 10 762,6 m3, installed 10 558 м3 of concrete (98,1%)
- according to the design - 2 874,9 tons, manufactured 2 825 tons of reinforcing roads (98,3%)

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 4921 m3 of concrete (64,1%)
- according to the design - 1 593,128 tons, manufactured 1270,147 tons of reinforcing roads (79,7%)

3. Installation of arch metal constructions (up to 1-st lifting)
- according to the design - 5 500 tons, installed 4802,64 tons (90,6%)

<

 

Select the another date

1. Installation of foundations in assembling area - completed

2. Installation of foundations in transportation area
- according to the design - 7 677,6 m3, installed 6 304,5 m3 of concrete (82,1%)
- according to the design - 1 593,128 tons, manufactured 1 492,221 tons of reinforcing roads (93,7%)

3. Installation of arch metal constructions (up to 1-st lifting) - completed; first lifting performed