At the end of November, ChNPP obtained the original copy of the license entitling the enterprise to process and store the radioactive waste which exists and results from Shelter facility transformation into an environmentally safe system.
Amendments were made to the license, and they are about extension of the implementation periods for a number of activities at New Safe Confinement-Shelter facility. Particularly, they include:
1. Extension of service life period for Shelter facility unstable building structures for another 6 years — up to 2029. Unstable building structures are the Shelter facility structures whose collapse probability is very high.
2. Development of a new design for unstable structure dismantling — to 2025.
3. Completion of unstable structure dismantling — up to October 31, 2029.


On November 30, ChNPP specialists participated in Round Table “Challenges of Fuel Containing Material Management”
In mid-November, two emergency drills were held at ChNPP. Two different facilities were chosen as training sites: Spent Fuel Storage Facility No. 1 and the Liquid Radioactive Waste Treatment Plant.
On November 22, a high-level opening event took place in virtual mode to kick off a series of activities on mental health support for operating personnel of NPPs in Ukraine.
On 14 November, the personnel of the Chornobyl NPP office in Slavutych participated in the special facility training. The drill involved employees following a designated route to reach radiation shelters, simulating actions in case of emergencies.